program committee convened in Madrid on April 11 and 12 to discuss the
proposals submitted for the summer 2005 scheduling
period . The committee was chaired
by Mario Tafalla (Observatorio de Madrid). The
principal investigators of each proposal will be informed by letter which
will include comments issued by the committee if there are any.
Plateau
de Bure Interferometer Proposals
A total of 54
proposals were received for the interferometer. The programs were classified
A (accepted), B (backup) and C (rejected). Programs rated A will be scheduled
in priority. Further time, if it becomes available, will go to the B programs,
taking into account scientific merit, crowding in certain right ascension
ranges and general aspects of balance.
For projects
rated A and B and without IRAM internal collaborator, please consult the
list of local contacts .
A: Accepted,
B: Backup, C: Rejected
|
Project
|
Rate
|
Project
|
Rate
|
Project
|
Rate
|
Project
|
Rate
|
Project
|
Rate
|
|
P001
|
A
|
P002
|
B
|
P003
|
B
|
P004
|
B
|
P005
|
C
|
|
P006
|
A
|
P007
|
C
|
P008
|
B
|
P009
|
A
|
P00A
|
B
|
|
P00B
|
C
|
P00C
|
-
|
P00D
|
B
|
P00E
|
B
|
P00F
|
C
|
|
P010
|
A
|
P011
|
A
|
P012
|
C
|
P013
|
B
|
P014
|
C
|
|
P015
|
C
|
P016
|
B
|
P017
|
A
|
P018
|
C
|
P019
|
C
|
|
P01A
|
C
|
P01B
|
B
|
P01C
|
C
|
P01D
|
C
|
P01E
|
-
|
|
P01F
|
C
|
P020
|
A
|
P021
|
B
|
P022
|
C
|
P023
|
A
|
|
P024
|
C
|
P025
|
C
|
P026
|
B
|
P027
|
C
|
P028
|
B
|
|
P029
|
A
|
P02A
|
C
|
P02B
|
A
|
P02C
|
C
|
P02D
|
C
|
|
P02E
|
A
|
P02F
|
A
|
P030
|
C
|
P031
|
B
|
P032
|
A
|
|
P033
|
B
|
P034
|
C
|
P035
|
A
|
P036
|
A
|
|
|
|
: some parts of the program - others rated B or C
|
104 proposals
were received for the 30m telescope, requesting 4491.6 hours of telescope
time. The highest rating "A" was given to 28 proposals ; 51
proposals were rated "B", i.e. were given backup status. The
remaining proposals, although scientifically valuable in most cases, were
rated "C". The individual ratings are listed in the attached
table. All A-rated proposals will be scheduled on the telescope, although
some with less time than requested. We expect that about half of the B-rated
programs will actually be scheduled. The selection will take into account
scientific merit, crowding in certain right ascension ranges, and general
aspects of balance. Proposals rated "C'' will not get telescope time.
The principal
investigators of each proposal will also be informed by letter which will
include comments issued by the committee if there are any.
|
|
IRAM 30m telescope proposal ratings : summer 2005
|
A
|
B
|
C
|
| 001-05 |
002-05 |
004-05 |
005-05 |
008-05 |
007-05 |
012-05 |
| 003-05 |
006-05 |
010-05 |
011-05 |
015-05 |
016-05 |
027-05 |
| 009-05 |
013-05 |
017-05 |
018-05 |
019-05 |
029-05 |
030-05 |
| 014-05 |
022-05 |
020-05 |
021-05 |
023-05 |
035-05 |
036-05 |
| 024-05 |
025-05 |
026-05 |
032-05 |
033-05 |
042-05 |
043-05 |
| 028-05 |
031-05 |
034-05 |
038-05 |
039-05 |
046-05 |
048-05 |
| 037-05 |
041-05 |
040-05 |
047-05 |
049-05 |
050-05 |
051-05 |
| 044-05 |
045-05 |
053-05 |
054-05 |
057-05 |
052-05 |
056-05 |
| 055-05 |
071-05 |
058-05 |
059-05 |
060-05 |
061-05 |
063-05 |
| 073-05 |
074-05 |
062-05 |
064-05 |
065-05 |
067-05 |
069-05 |
| 079-05 |
080-05 |
066-05 |
068-05 |
070-05 |
077-05 |
088-05 |
| 081-05 |
085-05 |
072-05 |
076-05 |
078-05 |
097-05 |
100-05 |
| 090-05 |
091-05 |
082-05 |
083-05 |
084-05 |
104-05 |
|
| 093-05 |
096-05 |
086-05 |
087-05 |
089-05 |
|
|
| |
|
092-05 |
094-05 |
095-05 |
|
|
| |
|
098-05 |
099-05 |
101-05 |
|
|
| |
|
102-05 |
103-05 |
105-05 |
|
|
|
Accepted
interferometer proposals which had requested time for measurement
of zero spacings will also get 30m time if they get observed at
Bure.
|
Roberto NERI, Clemens THUM