  1. ALMA project news: Brian Glendenning. See Brian's slides (note that the detailed numbers in the "breakdown" slides have changed a bit).
  2. Report on Calibration PDR and implications for software requirements
  3. Progress on High level software Analysis, see Joe's slides.
  4. Pipeline and off-line analysis requirements
    1. Pipeline requirements:
      • We had a discussion mainly on semantic issues -- are the calibration, quicklook and science data pipelines really pipelines? We decided to keep the name pipeline only for the whole thing, and separate the various pipeline operations by their nature and urgency: telescope/array calibration operations (quasi real time), processing of phase calibrators, quicklook operations, science imaging operations.
      • Should the quick look images be saved? the question arose but was not settled.
      • By default the image inserted into the archive should be the image as requested by the observer, not an image reduced in a simplified and standard way.
      • In order to ensure consistency of the requirements It was finally determined (by consensus) that the the pipeline requirements should be inserted in the General requirements (software memo 11) in place of the current section on the pipeline.
      • The original requirements should find their place in the new section.
      • Detailed comments should be handed to Frederic and Peter.
    2. Off-line analysis requirements:
      • We managed to discuss in some detail most of the requirements. They will be updated by S. Myers.
  5. Other issues:
    1. Connection to calibration group (to be formed): John Richer, Perter Schilke, Jeff Mangum, R. Lucas
    2. Operational Issues ASAC has started working on science operations (Neal Evans committee). John Richer participates; R. Lucas attends the phone meetings to present SSR views.
    3. Participation of SSR in reviewing the ALMA/AIPS++ test (this will be needed at the end of Phase I, november, and of Phase II, april): S. Myers, F. Viallefond, NN.
    4. Archive requirements will be revised and detailed by Ken Tatematsu + NN. This is in order to precise the relationship with the pipeline. These updated requirements too will go into the corresponding section of memo 11. This is distinct from the conceptual design of the archive (under way inside the computer group).
    5. Added Requirements linked to project extensions (ACA, future correlator) may have to be written. We will very probably have to start action on these issues in the fall.
    6. Next face to face meeting: in the beginning of 2002 (January?) i.e. after first work on pipeline concept, scheduling studies, ... the meeting place was not discussed yet. Any propositions?
    7. Next phone meeting in second half of August. I propose August 22 at 1500 UT

Action List

  1. R. Lucas to collect requirements updates in order to submit SPR's.
  2. S. Myers et al. to update Off-line requirements, before next phone meeting.
  3. P. Shilke and F. Gueth to update pipeline requirements (as a section in software memo 11), before next phone meeting.